At a glance
Before you begin
Service classification
Simple to Complex
Service sector
Environmental Management
Prepare your documents
Checklist of requirements
Bring the listed documents and secure them from the indicated office or source.
| CHECKLIST OF REQUIREMENTS | WHERE TO SECURE |
| Certificate of No Objection from the Barangay | Barangay Hall |
|
1. Land Title (1 photocopy)
|
Land Registration Authority (LRA) or Registry of Deeds (RD) |
|
5. Photocopy of Environmental Compliance Certificate (ECC) or Certificate of Non-Coverage (CNC) (if applicable) (1photocopy) |
Department of Environment and Natural Resources (DENR) |
What happens next
Process, fees, and timeline
Follow the citizen and agency steps in order. Processing time may depend on complete submissions.
| CLIENT STEPS | AGENCY ACTIONS | FEES TO BE PAID | PROCESSING TIME | PERSON RESPONSIBLE |
|
1. Proceed to the City ENRO, submit all the requirements |
1.1 Receive and review all the submitted requirements. If required documents complete, scheduling of site inspection. |
None | 1 hour |
Roan J. Pabilonia Czarina C. Jaballa |
|
2. Assist the inspectorate team |
2.1 Site Inspection | None | 1 day |
Roan J. Pabilonia Czarina C. Jaballa |
| 2.2 Preparation of site inspection report and clearance/certificate of no objection. | None | 15 minutes |
Roan J. Pabilonia Czarina C. Jaballa |
|
|
3. Pay clearance fee |
3.1 Prepare order of payment | Special Clearance – P500.00 |
Treasurer’s Office |
|
|
4. Receive the certificate of no objection/clearance |
4.1 Release of Certificate of No objection/clearance | None | 10 minutes |
Roan J. Pabilonia Czarina C. Jaballa |
| TOTAL: | Special Clearance – P500.00 | 1 day, 1 hour, 25 minutes | ||
| END OF TRANSACTION |
This digital guide reflects the Citizen’s Charter records published by the City Government of Tayabas. Offices may request additional supporting documents when required by law or by the particulars of a transaction.