At a glance
Before you begin
Service classification
Highly Technical
Service sector
Business-Friendliness and Competitiveness
Prepare your documents
Checklist of requirements
Bring the listed documents and secure them from the indicated office or source.
| CHECKLIST OF REQUIREMENTS | WHERE TO SECURE |
|
(Copy of Request Letter from concerned LGU-Office/Department/Agencies) (1 copy original) (Copy of Approved Budget (ABC, APP, PPMP) (1-Photocopy-each) (Copy of Certificate of Title, Deed of Donation and Other Related Documents) (1 - Photocopy - each) |
Requesting Agency Requesting Agency Requesting Agency |
What happens next
Process, fees, and timeline
Follow the citizen and agency steps in order. Processing time may depend on complete submissions.
| CLIENT STEPS | DEPARTMENT ACTIONS | FEES TO BE PAID | PROCESSING TIME | PERSON RESPONSIBLE |
| 1. Submit all the necessary documents needed for the preparation of plans and designs (Land Title, Deed of Donation, or any proof of ownership | 1.1 Review the submitted documents | None | 1 working day |
Kimwell B. Abelido |
|
1.2 Site Inspection Conduct project site visit to verify if the submitted documents is sufficient or intended for the proposed project |
None | 1 working day |
Kimwell B. Abelido Edison Q. Baasis Ar. Danica Irish E. Cabriga Aldrin A. Guaño Ar. Maristela R. Maaño Louide A. Pagana |
|
|
1.3 Survey Plan and Plotting of Lot Preparation of survey plan and plotting of lot |
None | 3 working days |
Louide A. Pagana Kivin O. Punzalan |
|
|
1.4 Checked and Reviewed Checking and reviewing of prepared survey plan and plotting of lot |
None | 2 working days |
Edison Q. Baasis |
|
|
1.5 Architectural Plans and Designs Preparation of complete of plans and designs |
None | 14 working days |
Benjamin N. Boitizon Jr. Ar. Danica Irish E. Cabriga |
|
|
1.6 Checked and Reviewed Checking, reviewing, and recommended for approval of prepared plans and designs to department head |
None | 2 working day |
Ar. Maristela R. Maaño |
|
|
1.7 Finalization of plans and designs/Revision Revision of plans and designs if applicable |
None |
3 working days (simple projects) 5 working days (complex projects) |
Benjamin N. Boitizon Jr. Ar. Danica Irish E. Cabriga |
|
|
1.8 Approval Prepared plans and designs for approval and City Architect will affix signature |
None | 1 working day |
Ar. Eladio V. Manzano Jr. |
|
|
1.9 Transmittal of complete set of final plans and designs Complete set of prepared plans and designs for transmittal to concerned agencies |
None
|
5 minutes |
Lorelyn N. Eroles |
|
| TOTAL |
None
|
27 days 5 minutes (simple projects) |
|
|
|
END OF TRANSACTION
|
|
|
Preparation of plans and designs for City funded projects requires thorough review and confirmation vis a vis set of parameters (budget) and request of the end user.
This digital guide reflects the Citizen’s Charter records published by the City Government of Tayabas. Offices may request additional supporting documents when required by law or by the particulars of a transaction.