At a glance
Before you begin
Service classification
Highly Technical
Service sector
Business-Friendliness and Competitiveness
Prepare your documents
Checklist of requirements
Bring the listed documents and secure them from the indicated office or source.
| Documentary Requirements | For more detailed list of requirements download to https://bit.ly/3UiOCRd or visit the Office of the Building Official at 2nd Floor Left Wing, New City Hall, Barangay Baguio, City of Tayabas. For further inquires, applicant may call (042) 793-2594, (0962) 136 8804 or send e-mail to buildingofficialtayabas@gmail.com |
| CHECKLIST OF REQUIREMENTS | WHERE TO SECURE |
| FOR TYPICAL SUBDIVISION | |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
|
Applicant |
: Development Permit - qualified for multi-stage processing
What happens next
Process, fees, and timeline
Follow the citizen and agency steps in order. Processing time may depend on complete submissions.
| CLIENT STEPS | DEPARTMENT ACTIONS | FEES TO BE PAID | PROCESSING TIME | PERSON RESPONSIBLE |
| 1 Preparation & Submission of Documents | ||||
|
1.1.1 Visit the office (Window) for the hard copy of forms and checklist
|
1.1 Give set of documents for construction permit application & assist client | None |
5 minutes
|
Allison R. Cuevas |
| 1.2 Prepare the necessary documents, sort and arrange according to checklist and secured each set with a staple or binder clip | ||||
| 1.3 Submission documents |
1.3.1 Checking the completeness of documents.
|
None None None |
20 minutes 5 minutes 5 minutes |
Allison R. Cuevas Allison R. Cuevas Allison R. Cuevas |
|
Internal Process
|
None | 5 minutes | Allison R. Cuevas Engineering Aide Building Official |
|
| Internal Process 1.3.3. Site Verification |
None | 1 day |
Engr. Zaldy R. Cademia Ar. Elizabeth D. Enriquez Ar. Mark Anthony M. Barquilla Engr. Gilbert T. Oabel Engr. Ara Tabitha A. Quevada Engr. Francis S. Pacaigue |
|
|
Internal Process
|
None None None None None |
19 days (in total) |
Ar. Elizabeth D. Enriquez Ar. Mark Anthony M. Barquilla Engr. Zaldy R. Cademia Engr. Ara Tabitha A. Quevada Engr. Gilbert T. Oabel |
|
|
Internal Process 1.3.5.2 If the application is not compliant,
|
None None None |
1 hour 5 minutes 5 minutes |
Engr. Francis S. Pacaigue Allison R. Cuevas Allison R. Cuevas |
|
| 1.4 Claim Transmittal Sheet, pull out plans/documents (if necessary) and sign the Transmittal sheet acknowledging receipt (Refer with your design professionals for your necessary corrections as indicated on the copy of Transmittal given) |
1.4 Assist Client in documents/permit forms/plans pulled-out for compliance |
None |
10 minutes (varies from |
Allison R. Cuevas |
| 1.5 Submit the corrected documents |
1.5.1 Check if corrections have been done.
1.5.3.1 Site Development/Topographical Map, Model Houses and other facilities
|
None None None
None None None None None |
10 minutes (varies from 5 minutes (varies from 3 days – in total (varies 5 minutes 5 minutes |
Allison R. Cuevas Allison R. Cuevas Ar. Elizabeth D. Enriquez Ar. Mark Anthony M. Barquilla Engr. Zaldy R. Cademia Engr. Ara Tabitha A. Quevada Engr. Gilbert T. Oabel Allison R. Cuevas Allison R. Cuevas |
| 2 Payment | ||||
|
2.1 Pay the Cashier (Window 4) |
2.1.1 Issue Official Receipt 2.1.2 Encode & Assign Development Permit Number 2.1.3 Print Certificate of Occupancy 2.1.4 Signing as approval of Development |
Refer to the schedule fees (National Building None None None |
5 minutes 15 minutes 5 minutes 10 minutes |
Treasurer’s Engr. Maria Leila P. Jarena
Engr. Francis S. Pacaigue |
| 3 Releasing of Approved Final Permit |
||||
|
3.1 Claiming of Approved Development Permit
|
3.1.Releasing of documents
|
None None |
10 minutes (in total) |
Allison R. Cuevas Allison R. Cuevas |
|
3.3 Bring the Approved Development Permit Form to OCPDC-Zoning & CDRRMO |
||||
|
3.4 Bring copy of signed Development Permit |
3.3 Received copy of signed Development Permit |
None |
2 minutes |
Allison R. Cuevas |
|
TOTAL |
Refer to the schedule fees (National Building |
For Highly Technical Transactions: |
||
|
|
END OF TRANSACTION |
|
This digital guide reflects the Citizen’s Charter records published by the City Government of Tayabas. Offices may request additional supporting documents when required by law or by the particulars of a transaction.